Tianjin Electric Power Construction – Heze 1000 kV Substation Project(96 units)

Apr 07, 2026

Project Overview

This project is part of a national key power infrastructure development—a 1000 kV UHV substation—with extremely high requirements for construction quality, delivery speed, and site image.

A total of 96 modular container building units were deployed to build an integrated modern office complex, including office areas, meeting rooms, and management spaces to support the entire project lifecycle.

With tight timelines and complex conditions, this project represents not just a temporary facility, but a comprehensive test of the contractor’s execution capabilities.

Location

The project is located in Heze City, Shandong Province, China, a key energy hub in East China, playing a vital role in regional power transmission and distribution.

 Scope of Supply

The scope of supply provided by Beijing JHHY Container House Co., Ltd. includes:

Design and manufacturing of modular container office units

Logistics, transportation, and on-site coordination

Rapid installation and system integration

Interior space planning (offices, meeting rooms, reception areas)

Integrated MEP systems (water, electricity, and infrastructure)

Solution

To address challenges such as poor geological conditions, difficult foundation treatment, and intensive cross operations, we implemented a highly integrated modular solution:

Factory prefabrication and rapid on-site assembly to minimize construction time

Standardized modular design for efficient execution under complex site conditions

Optimized foundation solutions to adapt to difficult ground conditions

Hour-level construction scheduling coordination

Full-process quality control meeting State Grid standards

Highlights

Ultra-fast delivery: Completed 96 units within less than 20 days

Highly competitive bidding: 4 out of 7 bidders withdrew in the first round

Intensive scheduling: Construction planned down to hourly coordination

High-standard compliance: Meets strict State Grid and joint office standards

Strong adaptability: Efficient execution despite complex site conditions

Benchmark project: A landmark modular office project in the industry

Client Value

This project delivered significant value to the client:

Accelerated project timeline, ensuring overall schedule compliance

Reduced construction risks and on-site uncertainties

Enhanced site image with modern and standardized office facilities

Improved operational efficiency for multi-team coordination

High-quality delivery, passing acceptance on the first attempt

leave a message

leave a message
For any request of information or technical support, fill in the form.All fields marked with an asterisk* are required.
Submit
Contact us #
+86-18630605462

home

products

whatsApp

Contact Us